Current:Home > reviewsGeorgia Power will pay $413 million to settle lawsuit over nuclear reactor cost overruns -WealthEdge Academy
Georgia Power will pay $413 million to settle lawsuit over nuclear reactor cost overruns
View
Date:2025-04-15 13:55:09
ATLANTA (AP) — Georgia Power Co. will pay $413 million to settle a lawsuit accusing the utility of reneging on financial promises to one of its nuclear reactor partners.
The payments to Oglethorpe Power Corp., announced Friday, could hold down future bills for millions of electric cooperative customers in Georgia.
Oglethorpe sued Georgia Power in June 2022 in a contract dispute over who should pay for cost overruns for a third and fourth reactor at Plant Vogtle, southeast of Augusta.
Atlanta based Southern Co., which owns Georgia Power, said it would write off a $152 million loss on the settlement.
Georgia Power also announced Friday that it must replace one of the four massive pumps that cools the Unit 4 reactor after operators found a problem with the pump’s motor during testing. Georgia Power said it believes the problem is an “isolated event” and has a spare pump on site, but said the replacement ends the company’s hope of placing Unit 4 in commercial operation this year. The utility said the reactor is still on schedule to begin operating by March. That was already the company’s fallback date.
Unit 3 entered commercial operation on July 31, becoming the first new nuclear unit built from scratch in the United States in decades.
Some Florida and Alabama utilities have also contracted to buy Vogtle’s power.
The overall project is seven years late and $17 billion over budget. Vogtle’s costs and delays could deter other utilities from building nuclear plants, even though they generate electricity without releasing climate-changing carbon emissions.
Oglethorpe, which generates and transmits electricity to 38 Georgia electric cooperatives that own it, will keep its current 30% ownership share of Vogtle under the settlement. Oglethorpe had originally sought to sell some of Vogtle’s generating capacity back to Georgia Power.
Heather Teilhet, Oglethorpe’s senior vice president of external affairs, said Oglethorpe wants to keep its 660-megawatt share of Vogtle’s generation to meet increasing demand.
“We are seeing growth on our system, so there’s great value in keeping our full Vogtle capacity, especially at a significantly reduced cost,” Teilhet said in a statement.
Currently, all the owners are projected to pay more than $31 billion in capital and financing costs, Associated Press calculations show. Add in $3.7 billion that original contractor Westinghouse paid to the Vogtle owners to quit building the reactors, and the total nears $35 billion.
Besides Oglethorpe and Georgia Power, Vogtle’s owners include the Municipal Electric Authority of Georgia and the city of Dalton. MEAG and Dalton also sued. Georgia Power agreed last year to pay up to $76 million to settle the lawsuit by MEAG, which provides power to 49 municipal utilities. The Dalton lawsuit is still pending, and Georgia Power said Friday that it could owe the city up to $17 million.
Georgia Power customers won’t pay for the settlements. Georgia Power has already reached a deal with regulatory staff about how much it will charge customers for Vogtle, although the elected Georgia Public Service Commission has yet to approve.
Georgia Power had agreed in 2018 that it would pay increasing shares of cost overruns for co-owners up to a certain ceiling. Beyond that, the co-owners were entitled to force Georgia Power to buy part of their ownership stake in exchange for Georgia Power covering all remaining construction costs.
Oglethorpe sought to activate the sale provision, saying it applied once construction costs reached a total of $19.2 billion. But Georgia Power argued the agreement didn’t kick in until construction costs reached $20.48 billion.
Under the agreement, Georgia Power agreed to pay Oglethorpe the $99 million Oglethorpe was owed under the cost-sharing ceiling, as well as $5 million in interest. Georgia Power has already paid part of that money and will pay the remaining $66.5 million within five days.
Georgia Power also agreed to pay 66% of Oglethorpe’s costs above the $19.2 billion level, a total of $346.3 million under projected spending levels. That includes a $241.2 million payment within five days. In exchange for keeping its 30% ownership stake, Oglethorpe is projected to pay another $179 million by the time Unit 4 is completed.
Oglethorpe’s total construction and financing cost for Vogtle is now projected to be $8.3 billion. That’s more than the $8.1 billion Oglethorpe projected it would owe, but less than the $8.64 billion that Georgia Power said Oglethorpe owed.
veryGood! (31)
Related
- Grammy nominee Teddy Swims on love, growth and embracing change
- Girl killed during family's Idaho camping trip when rotted tree falls on tent
- Hitmaker Edgar Barrera leads the 2023 Latin Grammy nominations
- The Versailles Palace celebrates its 400th anniversary and hosts King Charles III for state dinner
- DeepSeek: Did a little known Chinese startup cause a 'Sputnik moment' for AI?
- Generac recalls over 60,000 portable generators due to fire and burn hazards
- Powerball jackpot soars over $600 million: When is the next drawing?
- Khloe Kardashian's New Photo of Son Tatum Proves the Apple Doesn't Fall Far From the Tree
- Jamie Foxx reps say actor was hit in face by a glass at birthday dinner, needed stitches
- Influencer Remi Bader Gets Support From Khloe Kardashian After Receiving Body-Shaming Comments
Ranking
- Behind on your annual reading goal? Books under 200 pages to read before 2024 ends
- Colorado two-way star Travis Hunter to be out three weeks, coach Deion Sanders says
- Atlanta to release copies of ‘Stop Cop City’ petitions, even as referendum is stuck in legal limbo
- Lawsuit by Islamic rights group says US terror watchlist woes continue even after names are removed
- Tree trimmer dead after getting caught in wood chipper at Florida town hall
- FCC judge rules that Knoxville's only Black-owned radio station can keep its license
- Model Nichole Coats Found Dead at 32
- Why large cities will bear the brunt of climate change, according to experts
Recommendation
A Mississippi company is sentenced for mislabeling cheap seafood as premium local fish
Tia Mowry Shares Dating Experience With “Ghosting and Love Bombing” After Cory Hardrict Breakup
Network of ancient American Indian earthworks in Ohio named to list of UNESCO World Heritage sites
Once a global ideal, Germany’s economy struggles with an energy shock that’s exposing longtime flaws
Hackers hit Rhode Island benefits system in major cyberattack. Personal data could be released soon
International Criminal Court says it detected ‘anomalous activity’ in its information systems
Horoscopes Today, September 18, 2023
U.S. News' 2024 college ranking boosts public universities